(c) Paul Ott
Building construction
Nothing but the best for the youngest
Completed
Austria/­Großhöflein

New MAM Competence Center

Text Michael Windisch

PORR has built a new R&D centre for baby products manufacturer MAM in Großhöflein. The project put special emphasis on sustainability and flexibility of use.

As a global leader in the development and production of baby products, MAM takes the utmost care to combine functionality, attractive designs and high product safety standards. High quality is always MAM’s number one priority – there are no compromises in this regard.

Project data
  • Employer
    MAM Health & Innovation GmbH, Siegendorf
  • Contractor
    PORR Bau GmbH NL NÖ, Wr. Neustadt
  • Architect
    Innocad Architektur ZT GmbH, Graz
  • Order type
    Generalunternehmerin
  • Project type
    Building construction, Offices
  • Project scope
    Construction of a research and development centre
  • Order volume
    EUR 11.5 m
  • Construction start
    April 2020
  • Construction end
    November 2021
Download printversion

A strong and enduring interest in sustainable baby products and responsible practices is part of  the Austrian family-owned company’s DNA. The company, which has been committed to the well-being of the next generation since 1976 and now operates worldwide, has built a new research and development centre in Großhöflein near Eisenstadt to develop new products. Following a two-stage planning competition, PORR was awarded the contract to implement the project, which places great emphasis on sustainability, flexibility and high-quality fittings. The order volume was 11.5 million euros.

Sophisticated architecture and logistics

The building is made up of three interlocking cylindrical structures of different heights, the lower floors of which are cut into the natural slope. Construction began in April 2020, just as the coronavirus pandemic was beginning to spread throughout the country. Materials were scarce, and the approval process took longer than usual. Even the excavation work was a considerable logistical challenge, as the location of the structure in the upper part of the property meant that there was only one access route. The spoil also contained many large boulders, which meant that it could no longer be used as backfill material as planned. The entire structure was erected using the frame method, and slabs were used for the foundation. The load-bearing components are reinforced concrete columns, reinforced concrete walls and reinforced concrete floors. Creating the circular formwork, laying the radial and star-shaped reinforcement sections and laying the concrete core activation hoses in the ceiling put the team’s skills to the test. An access level was created around the structure in November 2020 to allow geothermal drilling to commence. Once the roof was watertight and the building shell was complete, the building was provisionally covered with tarpaulins and work began immediately on fitting out the interior. The floor-to-ceiling, panoramic wood and aluminium windows were installed during the winter months, the drywalls were produced, the rails for suspending acoustic baffles from the ceiling were mounted, and the ceiling was sprayed.

The floor plans of the three buildings are formed by intersecting circles. Spacious atriums are located at the respective centres of the circles. (c) PORR

Drilling deep

The screed was installed in the bathroom units in spring 2021. The laboratory and the office facilities were fitted with false floors with air ducts. After constructing the glass roofs and a slide, the 120m-deep boreholes for the 24 geothermal probes, which are used to heat the buildings in winter and cool them in summer, were completed. The distinctive sun protection louvres were then installed on the outside, while the glass walls were fitted on the inside. The baffle ceilings in the circular buildings are arranged in a star shape radiating from the centre of each circle. Suspended wooden ceilings were also installed and most of the exterior columns and drywall were clad in timber.

Complex technical facilities

High-quality technical facilities were very important to the client. In terms of technical building services, this included cooling ceilings, floor convectors, and false floors and shafts with air ducts. The installation of a KNX bus system for building automation, electronic access controls, audio systems in the meeting rooms, strip lighting in the offices and spot lighting in the traffic areas meant that the project also presented a considerable challenge in terms of electrical engineering. Grassy lawns planted with greenery, and ornamental gravel complement the circular company building.

The circular formwork, laying the radial and star-shaped reinforcement sections and laying the concrete core activation hoses in the ceiling put the team’s skills to the test.
Michael Windisch

Conclusion

PORR was tasked with reconciling the architects’ vision with what was technically feasible. The construction scheme was handed over in November 2021 to the complete satisfaction of all the parties involved. Due to the pandemic, the grand opening took place more than half a year later, in June 2022. Today, the Competence Centre in Großhöflein houses 75 workstations in the laboratories and offices, plus an underground car park, a product warehouse, engineering rooms, a reception area, a lounge, a kitchen, a gym, a roof terrace and an atrium with a slide.

Technical data

  • Bruttogeschossfläche
    3.688m²
  • Grundstücksfläche
    5.759m²
  • Aushub
    12.800m³
  • Verbauter Beton
    3.400m³
  • Verbauter Betonstahl
    335t
  • Solid glass walls
    720m²
  • Sun protection louvres
    1.430m²
  • Suspended acoustic baffles
    5.500m
  • Concrete core activation
    2.620m²
  • Geothermal probes
    24 Stk. a 120m

More articles

More projects

Exciting projects from the World of PORR.